Introduction And Scope
This method of
statement specifies the detailed requirements and procedures for the MEP
installation (Electrical Wiring For Lighting & Power Points) of the
above-mentioned project.
Methodology-for Electrical Wiring For Lighting & Power Points:
- Ensure all the related documents like currently approved shop drawings and load schedules are available with the installation team.
- Transfer the required number of wires from stores to the workplace.
- Before pulling wires, check and ensure there are no sharp edges or burrs to prevent damage while pulling wires.
- Identify the correct size and color. (Following the assigned/specified color coding) of wire, cut to the required length appropriately.
- Do not bunch two circuits together, if done so, for easy installation. shall be removed after installation.
- Pull the wires through conduits with the help of pull wires.
- Ensure no joints are made in any circuit.
- Leave a minimum of 250 millimeters in length or more according to the requirement which should be enough to connect to the desired terminals.
- Cover Conduit junction boxes with appropriate covers.