The Objective of this "Method Statement For Switch Gear Panels Installation" is to explain the details regarding the switch Gear Panels MEP, and installation work activities.
Purpose
The purpose of generating this method statement is to define the procedure step by step to implement the correct practices for the Installation of SWITCHGEAR PANELS INSTALLATION through the guidelines contained herein to ensure that the job execution complies with specifications and serves the intended function to a satisfactory level where applicable in the project building.
Scope
This method statement covers all processes related to the Installation of switch Gear Panels as the following:
Switchgear Panels Installation
- To make sure that the entire installation is in conformance and follows the design intent of the project for the Electrical and Low Voltage System (LVS) in addition to the specification/details and as per approved shop drawings and comply with local and International Standards (eg, CE & ISO).
- All the installation switchboards shall be installed and fabricated as per the manufacturer’s works/recommendations/requirements.
- Before beginning installation in any area, examine all parts of the adjoining works into which applicable work is to be placed. If any condition is observed which will prevent the proper execution of the work and or installation process shall not proceed in that area until such conditions and circumstances are addressed and corrected by the contractor.
- Fix all equipment independently of the wiring system. Use cadmium of zinc electroplated bolts, nuts, washers, and screws.
- Mount single DB at 1800 millimeters from finish floor level to the top of equipment, unless shown otherwise on drawing/schedules.
- Make sure that the clearance in front of the switchgear is not less than 1-meter, or as indicated.
- Number terminals, cables, and parts to correspond with the manufacturer have certified drawings.
- Terminate PVC, SWA PVC, and MICS cables inside the enclosure by securing cables to switchboards with gland brackets; and enclosure with glanding plates or fabricated steel extension boxes.
- For flush installation, DB’s all conductors shall terminate behind the board in an adaptable box. For surface mounting, trunking shall be fixed between the board and ceiling or floor level, or conduit runs directly into trunking which prevents correct installation of the trunking lid. Appropriate and essential earth continuity shall be made between the various components of the panels.
METHOD STATEMENT FOR SWITCHGEAR PANELS INSTALLATION |