METHOD STATEMENT FOR INTERNAL PAINTING WORK

The following method statement is for the Internal Painting Work. To download the complete file, click on the download link given at the end of the post.

1. PURPOSE

The Objective of this Method Statement for Internal Painting work is to highlight and explain in detail the procedure to be followed e.g., various types of paint and recommended surface preparation, in which to make sure that the Organization/Company’s compliance with the Occupational Health and Safety Requirements & Procedure and project specifications. 

2. SCOPE

The scope of this Work Method Statement (WMS) covers the works in any Project (Name of Your Project) plant as follows:

2.1. Painting Works for Exterior Walls, Interior Walls

3. STEP OF WORKS

3.1. Surface Preparation

3.1.1 Surfaces are to be prepared in accordance with good painting practices and in accordance with the technical product information sheets of the painting products.

3.1.2 Painting must not take place where the surface is moist or greasy or may become so before application of the first coat of paint (primer). 

3.1.3 Painting must not take place when the surface temperature is less than 3ºC above the surrounding air’s dew point, when the air relative humidity is higher than 85%, and when the temperature is below 5 ºC.

3.1.4 Prior to any application, the surface must be stable, firm, dry, and free of dust and concrete laitance. The surface must have no cracks.

3.2. Scaffolding and working at heights

3.2.1. Please refer to WMS for Scaffolding Installation.

3.3. Preparation of Coating Materials

3.3.1. All coating materials shall be thoroughly stirred in a container. Only approved thinners shall be used. Mixing shall be carried out in a well-ventilated area. See the painting product data and specification sheet for the mixing ratio.

3.3.2. During Mixing and Painting Application, an appropriate mask shall be worn in accordance with the recommendation of the approved MSDS. 

3.3.3. MSDS shall be available at the site and made known to workers.

3.4. Coating

3.4.1. Each coat shall be applied uniformly over the entire surface. Any imbalance surface shall be prepared by filling up using an approved Acrylic Filler, then apply to sand when dry and apply recoat. On beams, columns, and irregular surfaces, edges shall be coated with the recommended paint first and an additional pass made later.

3.4.2. Each coat shall be allowed to dry for the time specified by approval before application of any succeeding coat. See the product painting material/substances SDS and details also to verify Applicable Rate (AP) and Dry Film Thickness.

3.4.3. Any primer coat exposed to excess humidity or rain before drying shall be permitted to dry and the damaged area of primer should be removed to the bare substrate. 

3.4.4. Dust and lose particles shall be removed by using sanding till the surface is dry, sound, and wiped clean. Re-practice using the same primer and while dry practice paint filler to check for flat and clean surfaces. When the surface is ready to receive the topcoat then carried out the specified coating to satisfy DFT and specs.

3.4.5. Dust and loose particles shall be removed by sanding until the surface is dry, sound, and cleaned. Re-apply using the same primer and when dry apply paint filler to check for flat and smooth surfaces. When the surface is ready to receive the topcoat then applied the required coating to meet DFT and specifications.

3.4.6. The time interval between applications of two (2) successive coats must not exceed that specified by the product. Any coating shall be cleaned and freed from spray dust before the following coat is carried out.

3.4.7. Coatings shall be continuous which means free of pinholes, voids, bubbles, and other defects. 

3.4.8. Where the application is to be carried out by brush, brushes shall be of a type and quality as well as for using a roller which permits proper application of the material.

3.4.9. For spray application, spray guns, hoses, and pumps shall be cleaned before new material is added. An Appropriate moisture trap shall be used between the air supply and each application unit.

3.4.10. Specified film thickness for coating material shall be strictly observed. 

3.4.11. Dry Film thickness shall be checked with appropriate movie thickness gauges.

3.4.12. Before application of the final coat, all damaged areas shall be properly repaired using the original paint system.

3.4.13. Apply Acrylic Protective Paint for the exterior wall and use Acrylic Emulsion Resin for the interior wall

4. HEALTH, SAFETY, AND ENVIRONMENT 

Before commencing any work, the team shall strictly follow as per the Contractor Engr. & Procurement’s Health & Safety recommendations for handling and use of the materials. Make sure that all involved employees shall be well aware of the same. 

5. ATTACHMENT

5.1. Product Data Sheets & Material Safety and Data Sheets (MSDS)

5.1.1. Step ladders and extension ladders – to help you reach elevated areas

5.1.2. Paint scraper – to remove loose or peeling paint from wood, plaster, and other surfaces

5.1.3. Triangular-load scraper – to remove paint in small or tight areas

5.1.4. Steel wool – to remove corrosion from metal surfaces

5.1.5. Bristle brush – to clear loose material from masonry

5.1.6. Wire brush – to remove Sprouting and loose material from masonry, or to discard loose, flaking paint

5.1.7. Putty knife – to scrape away loose paint, or to apply filler

5.1.8. Broad putty knife – to fill in and smooth patching compounds in plaster and wallboard

5.1.9. Glazing compound – to replace cracked, broken, or missing panes of glass

5.1.10. Spackling paste – to fill nail holes and small imperfections in walls

5.1.11. Long-handled brush – to clean large exterior surfaces

5.1.12. Scrub brush – to remove mildew and dirt

5.1.13. Sandpaper (various grits) – to smooth and feather previously painted surfaces, or to roughen glossy surfaces so the paint will adhere better

5.1.14. Sanding block – to hold sandpaper and help you sand surfaces to an even finish 

5.1.15. Caulking gun – to apply caulk to cracks in walls, gaps, and seams in woodwork, and the junction of different surfaces (e.g., wood siding and stone)

5.1.16. Tubes of caulk – same as above (note that all acrylic and siliconized acrylic caulks are paintable; silicone caulk is not)

5.1.17. Masking tape – to protect window panes and trim from paint

5.1.18. Paint guide – to protect carpets and walls when painting baseboards and other trim

5.1.19. Roller tray and grid – to load rollers with paint

5.1.20. Brush comb – to clean paint brushes

5.1.21. Paint pail – to mix paint and carry it to the worksite

5.1.22. Drop cloths – to protect furniture, floors, and shrubbery from paint

METHOD STATEMENT FOR INTERNAL PAINTING WORK 





DOWNLOAD THE FILE HERE 👇

Post a Comment

0 Comments