RISK ASSESSMENT FOR WORK AT HEIGHT – LOW-LEVEL MOBILE TOWER SCAFFOLD

The following documents for the risk assessment "Work At Height – Low-level Mobile Tower Scaffold" are uploaded for our visitors in an editable and ready-to-use format. Click on the download link given at the end of these points.

Hazards

Use of low-level mobile tower scaffold

Consequences

  1. Worker falling from height due to handrails missing, whilst accessing the working platform, whilst erecting the tower
  2. Materials falling from the working platform onto persons or the ground below

Control Measures

  1. Ensure the tower is erected by competent, trained, certificated persons. Certification to be produced before erection.
  2. The tower is to be checked before use.
  3. The tower is to be tagged to identify it as ‘safe for use’, and the tower is to be inspected by a competent person every week.
  4. The top rail and intermediate rail are in place.
  5. An internal ladder is used to access the working platform. Operatives to alight the tower when moving/hatch closed on the platform.
  6. The exclusion zone is to be erected and signed to prevent access to the work area.
  7. Ensure toe boards are fitted (and correctly secured to the working platform) if the platform is above waist height.
  8. Work platform checked before use and kept tidy to prevent any buildup of materials.
  9. Remove all materials from the platform before moving.