VERTICAL TURBINE FIREFIGHTING PUMP INSTALLATION METHOD STATEMENT

 

VERTICAL TURBINE FIREFIGHTING PUMP INSTALLATION METHOD STATEMENT

Here's an Outline of the method statement for the installation of a vertical turbine firefighting pump:


Introduction:

This method statement provides a guideline for the installation of a vertical turbine firefighting pump. The pump will be installed in the pump room located in the basement of the building. The pump will be used to provide a water supply for firefighting purposes in the event of an emergency.


Scope:

This method statement covers the installation of the vertical turbine firefighting pump including the pump, motor, foundation, suction and discharge piping, electrical cabling, and accessories.


Procedure:


3.1. Preparation:

  • Before starting the installation, the following preparatory works shall be done:
  • Obtain necessary permits and approvals from the relevant authorities
  • Conduct a site survey to confirm the pump room dimensions and location
  • Ensure that the foundation is level and has the required dimensions and depth
  • Ensure that the pump, motor, and accessories are available and in good condition
  • Ensure that all the necessary tools and equipment are available


3.2. Installation:

The installation process shall be as follows:


3.2.1. Install the foundation:

  • Excavate the foundation to the required depth and dimensions
  • Ensure that the foundation is level and properly compacted
  • Install the foundation bolts as per the manufacturer's recommendations
  • Pour the concrete and let it cure for the required time


3.2.2. Install the pump and motor:

  • Assemble the pump and motor as per the manufacturer's instructions
  • Place the assembled unit on the foundation and align it with the foundation bolts
  • Tighten the bolts to the specified torque
  • Check the alignment of the pump and motor using a laser alignment tool
  • Install the coupling and shaft guard


3.2.3. Install the suction and discharge piping:

  • Install the suction and discharge piping as per the approved shop drawings
  • Ensure that the piping is properly supported and aligned
  • Install the valves and fittings as per the approved shop drawings
  • Test the piping for leaks and pressure as per the manufacturer's instructions


3.2.4. Install the electrical cabling:

  • Install the electrical cables as per the approved shop drawings
  • Ensure that the cables are properly supported and protected
  • Connect the cables to the pump and motor terminals as per the manufacturer's instructions
  • Install the electrical control panel and wiring


3.2.5. Install the accessories:

  • Install the pressure gauge, flow meter, and other accessories as per the manufacturer's instructions
  • Test the accessories for proper functioning


3.3. Testing and commissioning:

After completing the installation, the pump shall be tested and commissioned as follows:


3.3.1. Functional testing:

  • Test the pump for proper functioning
  • Conduct a pump performance test as per the manufacturer's instructions
  • Ensure that the pump is providing the required flow rate and pressure


3.3.2. Electrical testing:

  • Test the electrical connections and control panel
  • Ensure that the electrical system is properly grounded and protected


3.3.3. Commissioning:

  • Conduct a final inspection to ensure that the pump and its components have been installed properly
  • Obtain necessary approvals from the relevant authorities
  • Health, Safety, and Environmental Measures:
  • All necessary safety precautions shall be taken during the installation process
  • All personnel involved in the installation shall be properly trained and equipped with necessary PPE
  • All materials shall be handled and stored properly
  • Any hazardous waste shall be disposed of in an appropriate manner
  • All activities shall comply with the relevant environmental regulations


Conclusion:

This method statement provides a guideline for the installation of a vertical turbine firefighting pump. The installation process shall be carried out following this method statement and any applicable regulations and guidelines.