Here's an Outline of the method statement for the installation of a vertical turbine firefighting pump:
Introduction:
This method statement provides a guideline for the installation of a vertical turbine firefighting pump. The pump will be installed in the pump room located in the basement of the building. The pump will be used to provide a water supply for firefighting purposes in the event of an emergency.
Scope:
This method statement covers the installation of the vertical turbine firefighting pump including the pump, motor, foundation, suction and discharge piping, electrical cabling, and accessories.
Procedure:
3.1. Preparation:
- Before starting the installation, the following preparatory works shall be done:
- Obtain necessary permits and approvals from the relevant authorities
- Conduct a site survey to confirm the pump room dimensions and location
- Ensure that the foundation is level and has the required dimensions and depth
- Ensure that the pump, motor, and accessories are available and in good condition
- Ensure that all the necessary tools and equipment are available
3.2. Installation:
The installation process shall be as follows:
3.2.1. Install the foundation:
- Excavate the foundation to the required depth and dimensions
- Ensure that the foundation is level and properly compacted
- Install the foundation bolts as per the manufacturer's recommendations
- Pour the concrete and let it cure for the required time
3.2.2. Install the pump and motor:
- Assemble the pump and motor as per the manufacturer's instructions
- Place the assembled unit on the foundation and align it with the foundation bolts
- Tighten the bolts to the specified torque
- Check the alignment of the pump and motor using a laser alignment tool
- Install the coupling and shaft guard
3.2.3. Install the suction and discharge piping:
- Install the suction and discharge piping as per the approved shop drawings
- Ensure that the piping is properly supported and aligned
- Install the valves and fittings as per the approved shop drawings
- Test the piping for leaks and pressure as per the manufacturer's instructions
3.2.4. Install the electrical cabling:
- Install the electrical cables as per the approved shop drawings
- Ensure that the cables are properly supported and protected
- Connect the cables to the pump and motor terminals as per the manufacturer's instructions
- Install the electrical control panel and wiring
3.2.5. Install the accessories:
- Install the pressure gauge, flow meter, and other accessories as per the manufacturer's instructions
- Test the accessories for proper functioning
3.3. Testing and commissioning:
After completing the installation, the pump shall be tested and commissioned as follows:
3.3.1. Functional testing:
- Test the pump for proper functioning
- Conduct a pump performance test as per the manufacturer's instructions
- Ensure that the pump is providing the required flow rate and pressure
3.3.2. Electrical testing:
- Test the electrical connections and control panel
- Ensure that the electrical system is properly grounded and protected
3.3.3. Commissioning:
- Conduct a final inspection to ensure that the pump and its components have been installed properly
- Obtain necessary approvals from the relevant authorities
- Health, Safety, and Environmental Measures:
- All necessary safety precautions shall be taken during the installation process
- All personnel involved in the installation shall be properly trained and equipped with necessary PPE
- All materials shall be handled and stored properly
- Any hazardous waste shall be disposed of in an appropriate manner
- All activities shall comply with the relevant environmental regulations
Conclusion:
This method statement provides a guideline for the installation of a vertical turbine firefighting pump. The installation process shall be carried out following this method statement and any applicable regulations and guidelines.
0 Comments